Highlights: Winx-1
· Rig mobilisation commences
· Ice road and ice pad construction complete
· Cellar installation complete
· Spud scheduled for ~15th February 2019
Mobilisation of the Nordic Rig#3 commenced at 0845 1st February (AK time) from Deadhorse, Alaska. The mono body rig structure will now travel ~90 miles to the Winx-1 well site, travelling at ~1mph. Additional equipment required for the commencement of drilling is being mobilised to site concurrently in order to meet the scheduled spud date of ~15th February.